Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the bbpress domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/inspe.net/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the fluentform domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/inspe.net/wp-includes/functions.php on line 6121
High Luminosity LHC test bed enters final phase

High Luminosity LHC test bed enters final phase

The LHC test facility will remain in the testing and validation phase until the fall.
La finalización del banco de pruebas del LHC

CERN’ s technical teams are finalizing the interconnections on a 95-meter line that accurately simulates the new segments that will be placed on either side of the ATLAS and CMS detectors. This test bed is essential for the future of the collider.

Completion of the LHC test bed

The High Luminosity LHC(HL-LHC) aims to increase the integrated luminosity by a factor of 10, which implies a higher beam density and, consequently, a higher collision rate. To achieve this, superconducting quadrupole magnets made of niobium-tin have been developed, with capabilities to generate magnetic fields of up to 11.3 teslas, exceeding the 8.3 teslas of current magnets.

This development has been dubbed the “IT Rope”, a line that consists of six quadrupole magnets arranged in four cryostats, together with correctors and a dipole magnet to channel the beams in the direction of the collision points. All these components have been individually tested and are now integrated to simulate real conditions.

The cryogenic system will allow operation at 1.9 K, through the use of superfluid helium. superfluid helium. In addition, the infrastructure includes an innovative cryogenic feed line and a remote alignment system that can adjust the position of the magnets with an accuracy of 0.1 mm along the entire line.

This connection process includes some 70 interconnections soldered using specific techniques to ensure electrical continuity in superconducting circuits. Vacuum experts ensure the tightness of each joint before final closure. In addition, the controlled environment serves as a training platform for the technicians, who will then work in the tunnel.

The completion of the HL-LHC system. Source: CERN

Subsequently, complete cooling will be initiated, with the objective of energizing the magnets before the end of the year. This collective test will be important to optimize the final installation of the HL-LHC and ensure its operational success at the third scheduled long shutdown.